Precedence Diagrams Explained: A Comprehensive Guide

A precedence diagram is a graphical model that illustrates the activities of a project and their relationships. Applied in project management, especially in the Critical Path Method (CPM), it helps the team schedule activities effectively and identify potential bottlenecks. Understanding how precedence diagrams work can greatly improve project scheduling, resource allocation, and overall efficiency.

What Is a Precedence Diagram?

A precedence diagram, also referred to as the Precedence Diagramming Method or Activity-on-Node (AON) diagram, is a graphical representation of project activities that describes the relationships between them. It employs nodes to depict tasks and arrows to illustrate the relationships between tasks.

This method is widely applied in project scheduling using software like Microsoft Project, Primavera P6, and other project management applications.

Why Use a Precedence Diagram?

A precedence diagram is used for:

  • Clear Task Dependencies – Displays which tasks must be completed before others can begin.
  • Better Time Management – Enables the determination of the critical path, ensuring timely project completion.
  • Resource Optimization – Prevents the over-allocation of resources to overlapping tasks.
  • Risk Mitigation – Identifies delays and bottlenecks in the workflow.

Key Components of a Precedence Diagram

A precedence diagram comprises:

  • Nodes (Activities): Project tasks or activities.
  • Arrows (Dependencies): Indicate the dependency between tasks.
  • Task Durations: Each task is assigned a time estimate.
  • Critical Path: The sequence of tasks that determines the shortest possible project duration.

Types of Dependencies in Precedence Diagrams

Precedence diagrams describe task relationships in terms of four dependency types:

1. Finish-to-Start (FS) (Most Common)

Task B cannot start until Task A is complete.
Example: You can't paint a wall until you finish plastering.

2. Start-to-Start (SS)

Task B can start once Task A has begun.
Example: Report writing and report editing can be performed simultaneously.

3. Finish-to-Finish (FF)

Task B can be completed only after Task A is finished.
Example: Editing and uploading a video must be completed together.

4. Start-to-Finish (SF) (Rarely Used)

Task B must begin before Task A can be completed.
Example: A night shift worker must arrive before the day shift worker leaves.

How to Create a Precedence Diagram

 

  1. List All Tasks – Identify all the activities required for the project.
  2. Determine Dependencies – Define which tasks depend on others.
  3. Draw the Diagram – Represent activities as nodes and dependencies as arrows.
  4. Calculate Task Durations – Estimate the time required for each task.
  5. Identify the Critical Path – Determine the sequence of dependent activities that defines the shortest project duration.

Precedence Diagram vs. Gantt Chart

While Gantt charts provide a timeline view of tasks, precedence diagrams focus on task dependencies and workflow logic. Many project managers combine both to develop a comprehensive scheduling strategy.

Conclusion

A precedence diagram is a powerful tool for project planning. It helps teams visualize task dependencies and optimize workflow. Mastering precedence diagrams enhances efficiency, reduces risks, and ensures successful project execution.